March 03

Terrazzo and Mangum Street Project Updates

Terrazzo:

Our Terrazzo floor project in Building B is moving swiftly ahead.  Starting the evening of Monday, 3/6 through Wednesday, 3/15 work will be occurring in two separate phases that will restrict access coming off the passenger elevator and freight elevators on lobby level.  We recommend that you use the Level 4 service hallway off these elevators and come out by B401 to access Buildings A and B.  If you take the elevators to the lobby level you’ll need to cut through Social Table to access the main lobby concourse.  See below for the layout showing this work area and cut through of Social Table.

directions-around-terrazzo-j-and-k-00000002

directions-around-terrazzo-j-and-k-00000002

 

Mangum Street:

The final phases (two in total) of Mangum St. construction is upon us.

Phase 1: Starting 3/6/17, Mangum St. (from Elliott to Mitchell St.) will be closed until 4/1/17 for our final concrete paving application. During this time, traffic will be re-routed to Elliott St. as your path to Mitchell (see attached), much like we have done in the past.

Phase 2: Starting 4/1/17, North Mangum St. (from Elliott to Red Deck entrance) will have single lane closures until 6/1/17. Flagmen will be posted at each end to maintain the flow (again, much like in the past).

Detour signs will be posted and VMB’s routing everyone accordingly. See below for a diagram:

mangum-closure-3-6-2017

mangum-closure-3-6-2017